G2G Policy

The current Government to Government (G2G) arrangements are a direct threat to our country’s fundamental interests.

The key element of the G2G arrangement is that a larger, more advanced, country will assist a smaller, less-advanced country by building or operating complex facilities which are beyond the reach of the smaller state.

One of the features the G2G arrangements have in common with the other large-scale projects is the high degree of secrecy with which the proposals are developed.  That secrecy raises doubts as to whether proper Needs Assessments are undertaken and as to the degree to which the views of citizens and stakeholders are sought, far less considered.  The fundamental issue as to the necessity for these projects is thus routinely sidelined, which is inimical to the public interest.

The main criticisms of the G2G arrangements are –

  • Sidelining of the elementary Tendering Process – the procurement process is effectively outsourced, since the more powerful country has the right to select the contractor;
  • Limited, if any, role for Local Participation in terms of labour, professionals, suppliers, or contractors;
  • Weak or nonexistent contract controls, due to the disparity in power between the parties;
  • Serious drain on Foreign Exchange;
  • Lack of the promised Transfer of Technology.

These arrangements have been heavily criticised in our country for almost 35 years, starting with Winston Riley’s October 1979 paper which identified many of the emerging problems.  As a result of that rising tide of criticism, an official enquiry was established by then PM, George Chambers.  In March 1982, the Ballah Report was published and the G2G programme was brought to a halt as a result of its dire findings.

Despite the learning, successive political administrations seem unable to resist the appeal of these G2G arrangements, so we have today’s situation as shown in the table.

Physical Development Projects via G2G – April 2014

Readers who access this article online can view the background info via the hyperlinks

COUNTRY PROJECT/S DATE AMOUNT COMMENTS
CHINA NAPA – North & South 2008
  • TT$818M as’final cost’
  • TT$207M for ‘remedial works’
NAPA (POS) completed in 2009, NAPA (San Fernando) completed in 2012stated final cost of both projects was $130M USD ($818M TTD). A further $207M was borrowed from EXIM Bank of China in 2011 for ‘remedial works‘ on NAPA (POS). Design & Build contractor was Shanghai Construction Group.
AUSTRIA San Fernando Teaching Hospital 2011 TT$739M Opened in January 2014
CANADA Penal Hospital 2012 Undisclosed Involvement with Canada’s nominated designer SNC-Lavalin was discontinued after serious concerns over that firm’s international banning for corrupt business practices.
CHINA
  1. Couva Children’s Hospital,
  2. three national sports facilities in Couva,
  3. three multi-sports facilities in other parts of the country.
2012 TT$1.8 Billion Loan Agreement signed in March 2013 with EXIM Bank of China, with Shanghai Construction Group selected as the contractor for all the projects.These projects include the swimming & cycling complex at Balmain and the sporting complex at Tacarigua Savannah in Orange Grove.
CHINA Lake Asphalt 2013 Undisclosed MoU, with a Confidentiality Agreement, signed on 30 May 2013 between Lake Asphalt T&T Ltd and a Chinese contractor. One of the official objectives of the February 2014 State visit to China, according to the Office of the PM, was “…Removal of asphalt from the Pitch Lake in greater capacities…”.
CHINA La Brea Port and seven industrial parks. 2014 US$750M (TT$4.83 Billion) Agreement signed in February 2014 to have these facilities built by China Harbour and China Construction.

The total cost of these projects is just under $8.4 Billion TTD.
That is the background, against which we must consider these further elements –

  • china-caricomRegional Strategy – As a leading nation within CARICOM, it is important for Trinidad & Tobago to give serious consideration to the role of the various bilateral G2G arrangements China is pursuing in our region and the implications of those arrangements on our aspirations for healthy regionalism.  I have been reading the February 2013 Research Note by UWI’s Dr. Annita Montoute – ‘Caribbean-China Economic Relations: what are the Implications?‘  The scope of Dr. Montoute’s research and her findings are sobering – at pg 115  “…CARICOM Trade with China is on the increase; however it is overwhelmingly in China’s favour…”.  The regional issue is a serious one to which we must address our energies.
  • Trinidad & Tobago’s Strategy – Now consider these statements by then Finance Minister, Winston Dookeran, at the September 2011 ceremony to sign the $207M TTD loan for NAPA (POS) ‘remedial works’ –

    “…Dookeran said it was now imperative that TT deepens its ties with China…’In the first instance China has now emerged as a very significant player, especially in light of the recent tremors and uncertainties in the world economy,’ he said. ‘China…is now an economy that we will have to rely upon. It is in that context that it is very appropriate and timely for Trinidad and Tobago to start to intensify its relationship with China.’..”

    Winston Dookeran is now Trinidad & Tobago’s Minister of Foreign Affairs.

  • The Uff Report – The 42nd and 43rd recommendations of the 2010 Uff Report deal directly with this  issue –
    1. The Government’s policy on the use of foreign contractors and consultants for public construction projects should be transparent and open to review.
    2. Local contractors and consultants who compete with foreign companies should be provided with the same or equivalent benefits as enjoyed by those foreign companies and should be protected from unfair competition through matters such as soft loans…

    Uff was calling for the establishment of a national policy on this series of issues and the JCC has been requesting a consultation between government and stakeholders, so that a proper strategy can be developed in open collaboration. That would include labour, professionals, the State, the contracting sector and all the associated elements such as suppliers of building materials, financiers, skills training and so on.  The JCC wrote to the PM on this in April 2012, but to date there has been no response to our calls for those consultations in the national interest.

  • NAPA, again – The Minister of Culture, Dr. Lincoln Douglas, told the Senate on 8 April 2014 of the serious issues arising at NAPA (POS), with an estimated further $100M being required for more repairs.  It is not certain if the issues of disrepair are all due to inadequate maintenance, but it is unacceptable for such issues to have emerged for a structure less than 5 years old.
  • Shanghai Construction Group – Despite the bad record at NAPA, the selected contractor for the $1.8 Billion Couva Children’s Hospital and the other sporting facilities is the said Shanghai Construction Group.
  • Proposed Public Procurement Law – most alarmingly, Clause 7 of the proposed Public Procurement & Disposal of Public Property Bill 2014 specifically excludes Government to Government Arrangements and projects funded by International Financial Institutions from oversight.  That proposed exclusion is entirely unacceptable as it further jeopardises our national interest.

The PM has made a call for a National Conversation and this is one topic which needs addressing. Our country cannot continue exporting our jobs, capital and skilled people in favour of unexamined and undisclosed foreign policies.

The Elephant in the Room

The huge potential supply of State-built, unfinished office buildings in our capital is the ‘Elephant in the Room‘. There are potent elements at play here in terms of the viability of the long-term and large-scale investments which have been made in Port-of-Spain by private and public capital.

At this point, taking account of offices over 25,000 sf in size, there are over 1,500,000 sf of incomplete offices in our capital. This article will examine the likely outcomes for our capital and those investors as the various projects are completed.

Incomplete Port of Spain offices at February 2014 (Over 25,000sf)
Incomplete Port of Spain offices at February 2014 (Over 25,000sf)

The State has 1,329,000 sf of incomplete offices in POS and the private sector has 224,800 sf. The State has virtually seven times more incomplete offices than the private sector and that is the ‘Elephant in the Room’. This chart portrays the reality – the details are set out in the table below.

The legacy of the POS offices built during the previous administration is a matter which deserves serious consideration. The sheer volume of offices built by the State during the previous administration is sobering – 2.3M sf. Given that Nicholas Tower – that elliptical, blue tower on Independence Square – contains 100,000 sf, it means that the State built the equivalent of ‘23 Nicholas Towers‘ in our capital in that period of rapid development.

We also know that there was no attempt at public consultation or feasibility studies by the State or its agent, UDECOTT. At the Uff Enquiry, the Executive Chairman of UDECOTT, Calder Hart, admitted that a feasibility study had been done for only one of those projects. That project is the International Waterfront Centre (IWC), which comprises the two office towers of 890,000 sf, the Hyatt Hotel, New Breakfast Shed and car-parking/outdoor facilities. Hart also admitted, under oath, that the value of the land had been omitted from the viability study for the IWC, so it was a bogus exercise. The break-even rent is the amount which must be earned by a project to repay the cost of land, construction, professional fees and finance. The IWC, repeatedly boasted-of as UDECOTT’s flagship project, is not a viable project, since its break-even rent exceeds the highest rents now earned by A-class offices in POS.

The Parliament has now relocated there during the Red House repairs and renovations. A number of other Ministries and Public Bodies have also started to occupy those offices.

The Office of the Prime Minister is now in the new 75,000 sf building on St. Clair Avenue, opposite to QRC grounds.

The rationale advanced by the Manning administration for that surge in office construction in our capital is that it would free the State from the payment of large monthly rents to private landlords. Although I made several requests, I was never able to get the actual figures for the rents paid by the State in POS. My own familiarity with that market allowed me to estimate the average rent at that time (2007-2009) at about $8-9 per sf. The break-even rents of those new buildings exceeded $25 per sf, so the costs of those office projects would never be recovered. I have read reports that the estimated cost of the Government Campus Plaza, which is the largest element in the POS offices, was recently stated by UDECOTT’s Chairman, Jearlean John, to be of the order of $3.2 Billion.

We can reasonably estimate that the rate of rents paid by the State for office buildings has now increased since 2007, in terms of dollars paid per sf.

The completion of those State-owned office buildings is therefore a matter of the first importance, given the high carrying-costs. There is also the significant issue of the high opportunity cost of the State continuing to occupy rented offices alongside virtually-completed offices.
elephant tablet

Against this background, we are now seeing an active policy of decentralisation of POS offices by the present administration, with several Ministries and Public Bodies being relocated to south and central Trinidad. The decentralisation discussion is one which has been going on since the 1970s and it is an important issue to be pursued, in my opinion. That said, one has to wonder how is the decentralisation to be rationalised, given the existence of this over-supply of State-owned offices in our capital. That is a serious question which needs to be discussed if we are to achieve any proper resolution.

The completion of the State-owned offices is under the management of UDECOTT, the original developers, with recent disclosures from the Finance Minister of plans to sell the buildings and lease them back as a means of financing their completion. The terms of any such proposals would have to be carefully considered to avoid the mistakes and fraudulent behaviour of the past.

The completion and occupation of the State-owned office buildings in POS will pose an existential challenge to those private investors who have built offices for rent. The rental levels for offices in POS are likely to decline significantly, which will impact on the revenues of those investors.

CL Financial bailout – Paying the Devil

paying the devilToday is the 30th of January 2014: five years since the State bailout of CL Financial was announced to a shocked nation and region. It is necessary to mark this moment in time with solid facts and stern meditation.

The Carnival season is upon us, so J’ouvert is near the front of my thoughts. J’ouvert is simple, yet tremendous, because of the experience of passing from night into daylight and of course those around you becoming clearer as the light overcomes the darkness. For me, the defining feature of Jouvert is the terrifying portrayals of ‘Devil mas‘ in its various forms – ugly and dirty, covered with mud, oil or paint; real noisy, beating pitch-oil tins and such; forceful, in demanding payment from you before you could pass. You have to pay the Devil to go away. Pay the Devil, so he could leave without dirtying you up.

The vast amount of detail which has emerged in the last five years, means that I can only focus on one key aspect of the CL Financial bailout scandal.

My main theme is that vast amounts of Public Money have been committed to repay the debts of CL Financial, while the chiefs who directed and controlled that conglomerate seem free to come and go as they please. Or, in the case of Duprey, who refused to testify at the Colman Commission, to go and refuse to come. Once again, Trinis in the running for some awards for innovation and so on, with Duprey being the world’s first ‘Penniless Philanthropist‘.

How much Public Money has been spent on this exercise? How much of that Public Money will the State recover? That is my focus.

When the Memorandum of Understanding was signed on 30th January 2009, it was on the basis that CL Financial assets would be sold to recover the Public Money being advanced, which was estimated to be about $5Bn.

Winston Dookeran’s first budget speech on 8th September 2010 was a critical turning-point, as it appeared to me that he was attempting to stem the flow of Public Money out of the Treasury. Dookeran made a case which was based on the huge and unprecedented liabilities facing the State at pg 9 –

“…The total funding provided as at May 2010 by the Government and the Central Bank, excluding indemnities and guarantees to First Citizens Bank amounted to approximately $7.3 billion. As of June 2010, CLICO and British American combined total liabilities were approximately $23.8 billion but total assets were $16.6 billion…” .

Immediately, in protest at Dookeran’s attempt to limit the cost to our Treasury, there were several ‘Policyholders’ and Depositors’ groups‘ formed. The word ‘Depositors’ was soon omitted when it was realised that it would not suit their purposes.

With Dookeran isolated and the government under mounting pressure from these new protest groups, there were new laws drafted to stifle the protestors’ legal options. At this point, we had the historic address to Parliament by the PM on 1st October 2010 – historic because even with the required majority of votes to pass the intended new laws, the PM chose to explain and persuade the public. The bailout was extended to Hindu Credit Union and the Commission of Enquiry was announced to find the causes of the collapse of the CL Financial group and HCU.

Most notable was the PM’s outrage at the mystery of the bailout – at pgs 25-26

“…The $5 Billion has been spent—we are advised—to repay matured  EFPA policies in an ad hoc and unstructured manner where payment arrangements were entered into based on levels of funds invested. What criteria did you use to repay investors? Whom did you choose to pay? How were they chosen? These questions need to be answered. Because if it is today after the $7.3 Billion, all these EFPA people, the policy group and so on, they are out there, where is their money? Where is their money? Did you have a priority listing of who should be paid? Why did you go—and you are now crying crocodile tears about trade unions, credit unions, the poor man and the small man—why did you not pay them first? Why did you not pay them first? Where did that $7 Billion go? We need those answers, Mr. Speaker. We deserve those answers. The taxpayers need to know. Because when a parent  has to buy school books and bags to send his/her children to school but they have to pay tax out of the little money, they need to know where that money has gone…Where, how and why; we need to know…”

In September 2011 Parliament approved a new law authorising the State to borrow an additional $10.7 Billion to fund the bailout.

Winston Dookeran’s affidavit of 3rd April 2012 specifies that $24 Billion of Public Money is committed to the bailout, at paras 21 & 22…

Para 21         (a)      $5.0Bn already provided to CLICO;
                (b)      $7.0Bn paid to holders of the EFPA and
Para 22                  $12.0Bn estimated as further funding to be advanced.

Recent estimates have now risen to ‘$25b and counting‘ according to the Sunday Express report of 4th May 2013. Given the shock with which the estimated bailout cost of $5 Billion was received a mere five years ago, it is sobering that $25 Billion can now be bandied-about by Public Officials in this fashion.

Will our money ever be repaid? If so, how and when?

Now and again, official statements are made to assure the public that the matter is being resolved and the CL Financial Shareholders Agreement is extended for this reason or that. There is an appearance of diligence and purpose, but there are also other statements which we must consider.

Finance Minister Howai is recorded in Hansard of 30th January 2013, speaking about the CL Financial bailout – at pgs 16-17

“…Mr. President, we shall never recover all the funds that have been put into the group, but our focus is to try and maximize what we can and to reduce the borrowing that we need to do…”.

Even more concerning is that there has been secretive disposal of assets of the CL Financial group – to cite one example, Valpark Shopping Plaza was recently sold to Courts, without any public advertisement.

All the while, the State is mounting strong resistance to my lawsuit to force publication of the details of this bailout. The secrecy is inimical to the wider public interest, which is being sacrificed for the comfort and benefit of the ruthless few.

Every single established mechanism for oversight, transparency and accountability in public affairs has been sidelined in this sordid CL Financial scandal. Integrity in Public Life Act – nothing. Audited Accounts – not available. Freedom of Information Act – legally disputed. Briefing to Parliament – exempted.

Ask yourself – “Would you trust a public official with $1M to spend if there were no requirement for them to account properly?” If not, why should we trust any public official or institution with the authority to spend 24,000 million dollars with no oversight or accounting.

Hence my title – we really Paying the Devil.

cl-bailout-timeline

Letter to the Editor – UDECOTT’s failure to consult response

udecott-complaintIn response to a full page UDECOTT advert (embedded below) in response to my article “Invader’s Bay Review” (excerpted above), also published in the Business Express.

From: Afra Raymond <afraraymond@gmail.com>
Date: Sat, Dec 14, 2013 at 9:30 AM
Subject: Letter to the Editor – UDECOTT’s failure to consult
To: Editors of daily newspapers. Email addresses withheld

The 17th recommendation of the Uff Report is –

User groups and other interest groups should be properly consulted on decisions regarding public building projects, to ensure that relevant views can be expressed at the appropriate time and taken into account before decisions are made.

The decisive part is ‘before decisions are made.

The Peoples Partnership has not implemented the Uff Report’s 90 recommendations as promised and there has never been an explanation of that failure or refusal to carry out those critical measures. The sod was turned for the Couva Children’s Hospital on 2nd March 2012, at which time the project type, location, size, budget and procurement arrangements were all announced for the first time. Plainly, no consultation took place before those decisions were made, which was the point made in my 11th December article ‘Invader’s Bay Review’.

UDECOTT has now issued full-page newspaper advertisements to attempt to label my irrefutable observation as ‘reckless and damaging’ and so on. Yet another waste of public money, given that UDECOTT provided no examples of consultation before the key decisions were made on this huge project.

That pattern of secret development is inimical to our country’s progress. We must be properly consulted before decisions are made. We strongly criticised the last administration for that pattern of development and we will continue to make the same point. We must become a learning society.

Afra Raymond
POS

Invaders’ Bay Review

There now needs to be a complete and open review of the Invaders’ Bay matter. That is imperative if the public interest is to be safeguarded.

The catalogue of irregular dealings and improper procurement practice at Invaders’ Bay has now grown so that we are facing an important moment of decision. At this point there has been no announcement as to an award of contract or grant of any lease, so the threshold of binding legal agreement has not been crossed. In investment language, we are at the ‘inflection point’, which is where the prudent investor has to make a decision to continue or abandon a course of action.

This is the exact moment we should be calling for an open review of this major public project, before any binding commitments are made.

The Commission of Enquiry is an often-used device to probe into matters of serious public concern. In relation to construction and property development, we have had recent CoEs into the Piarco Airport Project, UDECOTT, Land-Date and the Biche School Project, to name a few.

The public has a sceptical attitude to these Commissions, since they never seem to bring the desired results in terms of arrests of prominent public officials or disgorgement of stolen monies. Many people dismiss CoEs as ‘talk shops’ set up to enrich lawyers, but I do not dismiss them as effective ways to serve the public interest. Despite the imperfections of the Enquiry process, including the fact that key witnesses can refuse to appear without incurring any serious penalties, there are real benefits. The main one, in my view, is that a CoE allows us in the public to learn about major matters of public concern which would likely have remained hidden.

That is the reason we need to retain this process so that the wrongdoing of the past can be exposed, so that we can have the possibility of avoiding those in the future. The weak point of the process is that it always takes place after the crimes have been committed, so during the Bernard Enquiry we were learning about the already-constructed Piarco Airport Terminal. Too late to prevent the massive theft and waste of Public Money.

That is why we need to consider a shift in our approach to the question of enquiries into questionable public projects, since the process is a reactive one, completely unable to stem wrongdoing.

At the ‘inflection point’ now occupied by the Invaders’ Bay project, we have an opportunity to examine this large-scale development before any significant expenditure of Public Money so that we can detect and deter wrongdoing. I am not yet settled in my mind as to exactly what type of review is best here, but whatever happens, it must be independent and committed to publication of its findings.

Some of the main issues which such an Enquiry or Review should examine are –

  • Consultation – The complete lack of consultation in this large-scale development proposal for our capital city would be addressed by the process. The land is vested in UDECOTT via a lease and that organisation has repeatedly claimed to have implemented the recommendations of the Uff Report. The 17th of those recommendations states “User groups and other interest groups should be properly consulted on decisions regarding public building projects, to ensure that relevant views can be expressed at the appropriate time and taken into account before decisions are made”. Given the swiftness with which the Couva Children’s Hospital – which is being executed via UDECOTT – emerged in March 2012, we know for sure that those recommendations are not being observed by UDECOTT. Even looking beyond UDECOTT and its conflicting ‘versions’, we can see the contradictory actions of the Ministry of Planning & Sustainable Development supporting a public consultation process at King’s Wharf in San Fernando, yet refusing to hold public consultations on Invaders’ Bay in Port-of-Spain.
  • Environmental Concerns – The Invaders’ Bay lands are extensive waterfront holdings in State property. The proper development of those lands must take full account of drainage issues and the impact on the environment, including the marine-life issues arising in any waterfront project. I have before me the EMA’s letter of 14 November, which confirms that there have been no requests or Certificate of Environmental Clearance (CEC) applications for the Invader’s Bay lands. In addition, the EMA records provided to me show that the most recent application for a CEC at Invader’s Bay was in January 2007. It is not possible to obtain planning permission without EMA approval, so there are other implications of the lack of these approvals.;
  • There is no link between the RFP and the other three strategic plans for the POS area. That violates the fundamental notion of strategic planning in that existing plans are ignored for no given reason. Piecemeal planning and development is detrimental to the Public Interest. So, who was the author of that RFP and who in the Ministry of Planning approved such a document?;
  • The Request for Proposals (RFP) published by the Ministry of Planning in August 2011 seeking Design-Build proposals for the development of these lands specified an entirely inadequate 6 weeks for submissions. Whose recommendation was it to truncate the development process in this fashion?;
  • The evaluation rules were only published after the closing-date for the tenders, so how did the proposers know what criteria to meet? That late publication is in breach of proper tender procedure, so the entire process is voidable and therefore illegal.
  • Legal Instructions and advice – Also critical to any review process would be the details of the legal advice sought and obtained at various stages of this process. The Ministry is adopting a bizarre, secretive stance in which the advice is claimed to vindicate their actions ‘thus far’, yet that legal advice is being suppressed. The JCC has taken legal action to challenge that unacceptable secrecy in this most public matter.;
  • Infrastructure – The 2014 Budget discloses a $50M allocation for infrastructure at Invader’s Bay, which of course is only a small part of this substantial cost. In the absence of environmental or planning approvals, it is difficult to establish the cost for proposals of this nature, since a design cannot be completed.
  • Allegations of squatting – Finally, we turn to one of the most vexed phrases in our lexicon where land is concerned. The issue of squatting, which is the unauthorised occupation of land not in your ownership. From the sequence of images shown below, we can trace some elementary conclusions:
    1. the first (left) is a map/plan, which uses a dotted line to illustrate the boundary between the Invaders’ Bay property and adjoining Port Authority lands to the north…the physical boundary is occupied by a watercourse/ravine and those ‘Port’ lands are occupied by MovieTowne/PriceSmart, a green play park and the Marriott/BHP-Billiton building
    2. the second (middle image) is an aerial photo which shows the Invader’s Bay land bare of vegetation
    3. the third (image at the base) is an aerial photo which shows the Invaders’ Bay land re-vegetated with mangrove and what appears to be a bare excision, immediately south of MovieTowne’s western carpark…that is a gravel-paved area, which is south of the watercourse I mentioned earlier…it is accessed via a basic bridge from the said MovieTowne carpark.

    (Click on images to expand)

    I am asking whether MovieTowne has a lease, licence or tenancy agreement to occupy those lands. Does MovieTowne pay any rent, licence fee or charge of any sort for the use and occupation of those lands? What action is UDECOTT taking on this? What action is the Commissioner of State Lands taking on this? It would be unacceptable for an entity in breach of State policy to benefit from the decisions of the State. I hope that is not what we are seeing here.

We need a full, independent and open review of this Invader’s Bay matter. Do you agree?

AUDIO: Heritage Radio Interview: Public Procurement, etc. – 04 December 2013

JCC President Afra Raymond interviewed on Heritage Radio 101.7FM by Hans Hanoomansingh to discuss JCC matters such as Public Procurement, Invader’s Bay and G2G Arrangements. 04 December 2013. Audio courtesy Heritage Radio 101.7 FM

  • Programme Date: Wednesday, 04 December 2013
  • Programme Length: 1:23:27

Secret Society

foiaThe State is the dominant agent in our national economy, which is the most vibrant in the Caribbean. It is therefore essential for us to understand how the State works so that we can better understand, or even plan, our interaction with that dominant party. Given the role T&T plays in the wider Caribbean, those concerns extend beyond our country to our region.

In order for us to understand how the State works, we must get quality information in the required quantities. We must also have the right to request further information from public bodies so that we can examine particular matters more closely – see Sidebar below.

This country’s Integrity Framework comprises elements such as –

  • The Integrity Commission (IC), which is responsible for monitoring the integrity of Public Officials;
  • The Freedom of Information Act (FoIA), which gives the right to ask for unpublished information;
  • The Auditor General, the Independent body monitoring the financial reporting of Public Bodies;
  • The Investments Division of the Ministry of Finance, monitoring the operations of State Enterprises;
  • The two Parliamentary Accounts Enterprises Committees, providing Parliamentary oversight of Public Bodies

This sustained examination of our country’s Integrity Framework is directed towards an enhanced level of information on how our nation’s Public Bodies are functioning. Continue reading “Secret Society”

CL Financial bailout – Really learning from the past

CB-gov - TTCSII am responding to the points made by Central Bank Governor, Jwala Rambarran, in his 6 November speech to the T&T Coalition of Service Industries.

This speech attempted to both re-affirm the Central Bank’s important role in our economy –

…as the country‟s prime financial regulator, the Central Bank has an almost fifty year record of maintaining the safety and soundness of the financial system…

and to distinguish Rambarran’s tenure as Governor since July 2012 –

…These are just a few of the initiatives the Central Bank has been working on over the last fifteen months to rebuild confidence, strengthen financial stability and to help create our future financial system…

Rambarran’s focus was “…First, “How did it all happen?” and, second…“What is being done to prevent a similar event from happening again?…” Continue reading “CL Financial bailout – Really learning from the past”

The Integrity Account

icttHaving completed my four-part series [1, 2 & 3, 4] on what I termed ‘The Integrity Threat‘, I was intrigued by two recent public notices on the meaning of the Appeal Court’s recent activity on these matters.

  1. 6 October  – The Integrity Commission issued a Public Notice which was a clear statement by the Commission that State Enterprises were within its lawful remit, according to the Appeal Court ruling on 27 June.  My reading of that ruling was that it effectively narrowed the 9th part of the Schedule to the Integrity in Public Life Act (IPLA) so that it only applies to Directors of Statutory Bodies performing public functions.  I maintain that view.  Even if one accepts the Commission’s reading of events, as set out in the exchange of emails in the sidebar, this ruling was a seriously retrograde step in the operation of our nation’s Integrity Framework, as I will illustrate;
  2. 5 November – the Judiciary issued a Media Release on the recent reports in other newspapers on a 28 October Appeal Court hearing on a 2006 Freedom of Information request made to TSTT.  I want to read the actual ruling/findings of the Appeal Court at that hearing before writing in detail on this.  Two things are clear – firstly, the Judiciary is able to set the record straight if there is a danger of the media misunderstanding important rulings.  That is the behaviour of a healthy Public Institution.  I am also noting here that the Judiciary has made no such efforts in respect of #30 of 2008, despite the several pointed criticisms in the media.  The second point is about the subject-matter of this lawsuit, which is the 2006 letter the Commission wrote to TSTT’s Directors confirming that they did not have to submit declarations.  That letter and the official efforts to conceal it, were the subject of this 7-year lawsuit.  I had raised this arrangement with senior officials of the Commission in earlier discussions, since it seemed incredible to me that TSTT could have gained such a concession.  I was told that the Commission had agreed to ‘hold its hand‘ since the issue was subject to the Court’s ruling – this is my paraphrasing of conversations, so of course I am subject to correction.  On the one hand I was recently told by the Commission that this arrangement was ‘in order‘ and on the other, it is now emerging that TSTT expended considerable time & money to conceal those details.  I am calling on the Commission to publish those details. Continue reading “The Integrity Account”

Invader’s Bay part 3: MORE Invaders Bay Ingredients

Invaders' Bay
Invaders’ Bay

I closed last week’s article by restating my view that all the ingredients for corruption were present at Invader’s Bay.

What are those ingredients?

Here is my list –

  • Extensive public assets coming onto the market, in turbid circumstances. Those assets can include property, concessions, contracts and jobs;
  • Questions of access to the gatekeepers – in these scenarios, some people will have unbelievable access to the decision-makers;
  • Conflicting and confusing versions of the project or proposal. The confusion is as persistent as it is deliberate, a part of the tangled web.
  • Blatant double-standards and lying is the norm in these situations;
  • Apart from ceremonial fluff, such as sod-turnings and ribbon-cuttings, there is no intention whatsoever to give any proper public account or statement of intentions. True transparency is evaded like taxes;
  • Professional Civil Servants who are unable or unwilling to insist on the maintenance of minimum standards;

Extensive Public Assets

These lands are estimated to be worth in excess of $1.2Bn at today’s priced, that means the unimproved value. Although the lands are reclaimed, a significant amount would have to be spent on infrastructure to make the property ‘shovel-ready’ for development.

As I noted in the first in this series, there were conflicting claims on this aspect, with the selected developers claiming extensive infrastructure expenses as a way to reduce what they would pay for the land. There were no estimates given for the developers’ cost of infrastructure, but I noted that the National Budget for 2014 had specified, at pg 89 of the Public Sector Investment Program, that there would be publicly-funded ‘Infrastructure Development’ at Invader’s Bay.

I have been assisted by some of the professionals in the very Ministry of Planning & Sustainable Development in identifying that item as being a $50M allocation for 2014. The actual works are unspecified, so it is difficult to be certain what is included. It certainly seems a modest sum given the size and peculiar challenges posed by the Invader’s Bay property.

In addition to the obvious public asset of the actual property, readers should note that assets in this context can include concessions. In this context that can mean maritime & docking concessions as well as tax concessions, so we will have to maintain full vigilance to safeguard the public interest.

As a first position, all the details of the overall agreements must be published for public consideration at the earliest opportunity. This is no minor point, since really huge sums of wealth can be transferred from public hands to private interests if proper transparency is not ensured. Just remember that in June this year while the President of the Peoples Republic of China was here there was the signing of a Government to Government Agreement. The JCC has lodged many strong objections to those agreements. How many readers will remember that there was an important agreement signed with respect to the Pitch Lake at that time?

To cite a press report

…According to a release from Lake Asphalt of Trinidad and Tobago (1978) Ltd, the signing ceremony of a Memorandum of Understanding and a Confidentiality Agreement with Beijing Oriental Yuhong Waterproofing Technology Co Ltd of the People’s Republic of China is scheduled to take place at the Hyatt Regency, Port of Spain…

So, faced with a Freedom of Information Act which ensures disclosure, the new trend is to wrap-up the details in yet another layer of secrecy. We need to be alert to that trend. After all, this is the same Ministry which claims to have legal advice confirming that its actions conform to the Central Tenders Board Act, yet steadfastly refuse to publish that advice.

Access to the gatekeepers

One of the two successful proposers has been the MovieTowne principal, Derek Chin, whose confidence has been striking.
According to Mr. Chin, in an extensive interview

…Chin has met with the Prime Minister and many government ministers seeking approval for this project.
Before Christmas 2010, he had a meeting with the Transport Minister Jack Warner, Foreign Affairs Minister Suruj Rambachan, and other ministers, at the Prime Minister’s Office. They all supported his plans. “I have been lobbying the Government for a year now, even before the elections. I sent in the preliminary sketches about the concept; I met 19 Cabinet ministers over the last six months. The next minister I am meeting is Bhoe Tewarie, Minister of Planning. He wants to see me. I also met with Jearlean John, Udecott chairman. She also loves it, but that was three to four months ago…

That interview was given in early July 2011, which is over one month before the Request for Proposals was published by the Ministry of Planning & Sustainable Development at the end of August. I tell you.

Conflicting and confusing versions

So, to return to the legal opinions, we have this swirling set of stories.

To date, Minister Tewarie has insisted that the project has been removed from UDeCoTT’s portfolio and placed within the Ministry of Planning. He claims that Cabinet approved this in 2011 and also insists that there is no tender process at Invader’s Bay. Of course it is impossible for the Ministry to proceed to invite tenders for anything without following the Central Tenders Board Act.

The first legal advice I saw was clear that there is indeed a tender process at work here and that the CTB Act ought to have been followed. Obviously, that conclusion did not ‘fit the script’, so an escape hatch had to be fashioned. Shortly thereafter another opinion was submitted by Sir Fenton Ramsahoye SC, on an entirely different set of assumptions which made UDeCoTT the central enabling agency in the entire scheme.

The approach endorsed by the Ramsahoye opinion flatly contradicts the version being advanced by Minister Tewarie.

That is the deep, intentional confusion being encouraged by public officials in this matter.

Blatant double-standards and lying

So, let us start with the role of the Ministry of Planning & Sustainable Development on the Invader’s Bay project. How does that Ministry reconcile its active role in seeking public views on the King’s Wharf project in San Fernando with its silence on Invader’s Bay in POS?

These are blatant double-standards of the worst kind. One can scarcely believe that there are professional civil servants who could condone this reckless and underhanded approach to national development. But there we have it.

When is the Ministry of Planning & Sustainable Development going to host a public consultation on Invader’s Bay? That is now an inescapable requirement. Sooner rather than later.

But that is not all. No, not at all.

This administration campaigned on the findings of the Uff Enquiry and made several public promises to implement the 91 recommendations of the Uff Report. Such was the importance of the matter in the political agenda that it formed the first item of the very first post-Cabinet Press Briefing of the Peoples Partnership administration on 1st July 2010. That is a broken promise, since those Uff recommendations have not been adopted and the JCC’s many attempts to offer our assistance to achieve that have all been rejected.

The 17th recommendation of the Uff Report is –

  1. User groups and other interest groups should be properly consulted on decisions regarding public building projects, to ensure that relevant views can be expressed at the appropriate time and taken into account before decisions are made…

There has been no consultation at all on the Invader’s Bay proposals. Quite frankly, apart from rumours and conflicting press reports, I do not really know exactly what is going to be built or where or even when.

According to the iconic American jurist Louis Brandeis, speaking on eradicating corruption –

‘Sunlight is the best Disinfectant’